In order to guarantee local residents and tourists easy and stress-free transportation during the Spring Festival Golden Week, the reconstruction project of wastewater separation infrastructure in Sanya city will be completed before December 15th, nearly two years earlier than planned.

By October 30th, about 480 million yuan had been invested on the project since it started construction on April 15th 2013, and 75% of the total engineering work has now been completed, according to a head of the Sanya Housing and Construction Ministry.

With a total investment of 660 million yuan, the project focuses on the reconstruction in Xincheng Road, Sanya Bay Road, Haihong Road, Jinjilin Road, Youyi Road, Jixiang Road, Fenghuang Road, Linchunhe Road, Hexi Road and Yingbin Road, with the building of a new 77.9-kilometer pipe and the cleaning of an old 26.5-kilometer pipe.

 
SOURCE: WOS Team
 
Editorial Message  
News translation appearing here is the property of www.whatsonsanya.com, however, for those who wish to copy the contents in part or in full, please make reference and link the article copied to our site. Whatsonsanya.com does not necessarily endorse their views or the accuracy of their content. For copyright infringement issues please contact editor@whatsonsanya.com