The Hainan liquefied natural gas (LNG) project, construction on which began in August 2011, is expected to be completed and start production in August 2014.

With a total planned investment of over 6.5 billion yuan, the LNG project consists of three parts, the Liquefied Natural Gas Terminal construction, the port engineering construction and the pipeline construction, which started this March and is expected to be finished in June 2014.

As of the end of May, the Hainan government has already invested 2.48 billion yuan in the LNG project, and 54.09% of the total engineering construction has been completed.

  
SOURCE: WOS Team
 
Editorial Message  
News translation appearing here is the property of www.whatsonsanya.com, however, for those who wish to copy the contents in part or in full, please make reference and link the article copied to our site. Whatsonsanya.com does not necessarily endorse their views or the accuracy of their content. For copyright infringement issues please contact editor@whatsonsanya.com